880 Zone & Hwy 75 Pump Station Improvements

Project Location: Waxhaw, NC
Project Type: Public Utilities
Client: Union County Public Works
Total Contract: $4M+

RTD is Prime Contractor on a new booster pump station facility and ancillary upgrades for Union County, North Carolina. Project hi-lights include;

880 Zone Development

  • New 880-Zone booster pump station facility, underground piping, engine generator, electrical system, instrumentation, and site work
  • Install metering valve vault with associated piping
  • Tie-in to existing 24" main along Providence Road
  • Development of new 880 Pressure Zone by constructing four pressure regulating valve stations, including buried valves and vaults

Highway 75 Pump Station Improvements

  • Replacement of butterfly valves inside pump station 
  • Install metering valve vault with associated piping
  • Electrical improvements, including new automatic transfer switch and standby engine-generator

RTD self-performed 65% of all the work including all formwork, concrete work, sheeting and bracing, excavation & backfills, site work, yard piping, setting of valve vaults, generator installation, pumps installation and all process piping.